Getting started with Gantt scheduling

You can use Helix Plan to plan your projects using Gantt scheduling. This works by adding scheduled tasks, which can be connected to other tasks to create dependencies and sort tasks chronologically. For example, if one task requires another to be completed first, you can connect the two and set their respective start and end dates. To add new tasks in the Gantt scheduling mode, refer to Creating scheduled tasks.

When you are making a project plan and assign tasks to users or change anything, those changes will take effect immediately across the entire project server.

Projects can have several project managers, each with their own project plan.

If you want to co-ordinate between several project managers in the same project, you can use the Portfolio allocations tool. See Portfolio allocations.