Creating an Interrupt Intermediate event
To create an interrupt intermediate event in a task or a collapsed subprocess:
1. Select the intermediate event icon in the toolbar.
2. Click the task or collapsed subprocess for which you want to create an interrupt intermediate event.
To create an interrupt intermediate event (or another intermediate event) in an expanded subprocess:
1. Select the intermediate event icon in the toolbar.
2. Click the bottom border of the subprocess.
If you click elsewhere, you create an intermediate event that is not an interrupt intermediate event.