Managing users in Agile projects

Japanese version

It is generally advised to allocate a specific set of users or user groups to a sprint. This can be important when you have separate parallel programming and art sprints.

Accessing the user allocation dialog

Right click on the sprint, and select Allocate users to sprint in the context menu. You can also right click on a single user in the People list, and select Allocate users to sprint.

Allocating users to sprints also enables use of the work remaining column. When users update the estimated work remaining, the user allocation meters on the timeline part of the schedule is also updated to reflect the total work remaining for each user. Additionally, the portfolio section of Hansoft accurately reflects the user allocation across the entire portfolio.

Set allocations by right-clicking a user.

Users can be allocated by a percentage, to accommodate the fact that users can work on several sprints in parallel, or that users might have responsibilities outside of the sprint work.

The following image shows a part-time allocation to a sprint.

Clicking a user in the People section will display a summary of tasks for that user in the sprint. Tasks that are the allocated time will be displayed in red.