How To: Using the same priority column in both Product Backlog and Planning View

Note: Only Main Managers can do this.

By default there are two distinct priorities in Hansoft, (1) the product backlog priority representing business value and (2) the sprint backlog priority more often associated with technical delivery.

When conducting sprint planning it can sometimes be useful to have the Product Backlog Priority side-by-side with the Sprint Backlog Priority. This is how you set this up.

Note: After these changes you will have to reprioritize your product backlog (which sometimes is a good thing).

Step 1: Create a custom priority column

Step 2: Replace the default product backlog priority column

Step 3: Create the column in the planning view (again)