Burndown prediction

Japanese version

Burndown prediction is calculated using a weighted average. This topic explains which calculations Hansoft performs to determine the "Predicted velocity" in a burndown chart.

You can customize prediction settings in the Customize Project dialog box.

This example will use a sprint prediction of "3 days weighted average".

Weekends and holidays

The first thing to be aware of is that Hansoft ignores "Free days" such as holidays and weekends when predicting velocity.

Weekends are easy to identify by their darker shade of gray in the timeline.

The calculation

Velocity Day
0 1
-22 2
-11 3

The equation would then look something like this when we add values: