Project history
With the Project history tool you can save and view snapshots of the project for a specific date and then compare it to the current version. Project managers can analyze slippage of releases, user groups (such as programmers), individuals, sub-projects or specific tasks.
Before a user can work with project history, an administrator must give them access to it. See Changing project user settings.
To access the Project history, open the Product backlog or Planning views and select More > Project history or More > Product backlog history.
- View product backlog history / Planning view history - For more information, see Viewing project history.
- Save product backlog in project history / Save a snapshot in project history - For more information, see Saving a project history snapshot.
- Project history auto-save options - Choose how often the project should be automatically saved to the project history. You can also turn off auto-save entirely. For more information, see Setting project history auto-save options.
Before making major changes to the plan, save the current plan by pressing Ctrl + K (Cmd + K). If you are not satisfied with changes, go to the project history, copy the changed items, and then paste them in the current project view. You can also export and import items to move them between servers.