Switching between Agile and Gantt scheduling modes

You can use both Agile and Gantt scheduling in one Helix Plan project. Each project will have a default mode, which is set by the administrator who creates the project - see Creating new projects for more information. However, all users can use both modes and switch between them at any point.

To switch between Agile and Gantt scheduling modes in the Planning view, use any of the following methods:

  • If in Agile mode, click Agile Schedule and choose Switch to Gantt scheduling interface. If in Gantt scheduling mode, click Gantt Schedule and choose Switch to Agile interface.
  • Click More and choose Switch to Gantt scheduling interface or Switch to Agile interface.
  • Press Ctrl+W (Windows and Linux) or Cmd+W (Mac).